Final rule: revival and late-payment petitions need more explanation after one year of delay

Petitions based on unintentional delay, such as reviving an abandoned application, paying a late maintenance fee, or adding a late priority claim, now require additional information once the delay exceeds one year instead of two. The fee conditions also changed.

Published
Effective

When a deadline is missed unintentionally, the USPTO lets you fix it by petition. This covers reviving an abandoned application, accepting a late maintenance fee, accepting a delayed priority or benefit claim, and some international design deadlines.

What changed

  • Additional information threshold cut from two years to one. If the delay between the missed deadline and the petition is more than one year, the USPTO requires additional information showing the entire delay was unintentional. Separately, the Director can still ask for more information in any case where there's a question whether the delay was unintentional.
  • Higher fee after one year. The larger petition fee under 37 CFR 1.17(m)(1), $3,000 undiscounted ($1,200 small, $600 micro), now applies when the petition is filed more than one year after the missed due date, instead of two years. Petitions filed within one year pay the 1.17(m)(2) fee of $2,260 ($904 small, $452 micro). The fee amounts themselves didn't change.
  • Effective August 13, 2026, for new petitions filed after that date. It covers revival under 37 CFR 1.137, delayed maintenance fees under 1.378, delayed priority and benefit claims under 1.55(e) and 1.78, and excusing a failure to act in an international design application under 1.1051.

What to do

  • Treat any abandonment or missed maintenance fee as urgent. Filing within a year keeps the petition simpler.
  • If you're past a year, include the required explanation with the petition, with dates, when the missed deadline was discovered and what was done afterward.

See our guide to patent term and maintenance fees for the maintenance fee windows.